Skip to content

Project Basic Setup#

Jobs Setup#

In the "jobs-setup" the necessary settings for the later project creation and implementation are made.

KUMAVISION factory365 - Plant Engineering extends the Projects facility of Microsoft Dynamics 365 Business Central1 with the fields described below:

FastTab Numbering#

Field Description
Project Location Number Series Specifies the number series to be used for assigning the project storage locations.

FastTab Plant Engineer#

Field Description
Project Type Dimension If you define a dimension here, you can define in the project types which dimension value for the dimension should be assigned to a project by the system when assigning the project type.

By setting project type dimensions, you can create analyses about your projects according to the dimension value.
Check Resource Qualification When entering a resource in the project plan lines, the system checks whether the necessary qualifications for an activity type are available.

The following selections are available:

No
check is made when resources are used

Planning onlyWhen
maintaining project plan lines, the resource is checked against the necessary qualifications

Booking onlyIt is
checked for the sufficient qualification at the time of booking

Planning and BookingCombination of
Planning Only and Booking Only
Allow Synchronisation from Sales Defines whether the synchronisation of a project plan line from sales is permitted.

FastTab Dispatch#

Field Description
Create Project Location For the procurement and logistics processes, you use this to specify whether the system should create a project storage location for each project.

The project storage location hereby represents the place of performance of the project.
Standard Project Location Defines the template project storage location, which can be selected from the "Storage locations" overview.
Standard Transfer-from Location The field is a selection list of all regular storage locations (no project storage locations). It specifies the stock transfer route and is transferred to the "Stock transfer from storage location code" field on the "Invoice and dispatch" info tab of the project card.

FastTab Outlook ToDos#

Field Description
Step CRM task If you are working without a project outline, use this field to specify the increment for creating new project tasks.
Separator CRM task If you work without a project breakdown, use this field to specify the separator for creating new project tasks.
Counter CRM task If you work without project breakdown, set the counter for creating new project tasks in this field.

Project accounts#

In the projects for plant construction, consumption and sales postings are displayed on a project chart of accounts, which is used for project controlling. The selection of the corresponding project accounts is controlled via the project account setup.

Project Chart of Accounts#

The project chart of accounts is used for project controlling and contains all sales and cost accounts that are to be used for a differentiated project view. The project chart of accounts is not dependent on the FIBU chart of accounts.

In the "Account type" field you can choose between five options:

Field Description
Account A bookable account can be selected.
Headline Text line in which a heading can be entered as a structure feature.
Total A sum defined by the "Total" field.
From-Sum An initial marker for a totaling project account series that ends with the To Total account type.
To-Sum An end marker for a totalizing project account series that starts with the From Total account type. The total is defined using the Totalization field.

After you have set up the project account, select "Actions" > "Indent Chart of Accounts" in the ribbon. Then select the "Yes" option in the message window.

Project account setup#

The procedure is almost identical to setting up the posting matrix in the financial accounting area.

The project account setup determines the project accounts to which consumption and revenue are posted or budgeted in plant construction. The project account setup is a matrix that defines the consumption and sales accounts for product posting groups.

The project type is taken from the project card when accessing the project account setup. The activity type, on the other hand, is taken from the project task line.

If no match is found using the project type, activity type and product posting group, an error message appears.

Each project item is assigned either a consumption account or a sales account depending on its item type (consumption or sales). The field contents of the project item are used to determine the project account.

Project Roles#

The project roles define in the later projects which role (e.g. project manager) the resource takes in the respective project.

To define the project roles in advance, call them up via the user search. Via "New" in the menu ribbon you can create a new project role with the help of the table below.

Field Description
Code Assign a meaningful abbreviation for the project role.
Description Assign a description for the project role.
Type Assign an applicable type. You can choose from the following:
• Responsible
• Project Manager
• Sale to contact no.
• Invoice to contact no.

Service type#

It is important for the later task planning in the projects to set up the activity types. To do this, call up the activity types via the user search.

Via "New" in the menu ribbon you can define a new service type with the help of the table below.

Field Description
Code Assign a meaningful abbreviation for the activity type.
Description Assign a description for the service type.
Type Specifies the type that the record is. You can choose from the following:

• Account
• Headline
• Total
• From-Sum
• To-Sum
Counting up Here you can now specify the interval or other filter specification of numbers of the service type.
The results of the specified service type are added to a total balance.

For the From sum or Heading type, this field must be left blank.

For the To-total type, the field is automatically filled when the chart of accounts is indented. Only the types that are between a From total and a To total are added together.
Qualifications Indicates the number of qualifications required for the service type.

Via a LookUp on the number, qualifications can be assigned to the activity type and already existing ones are displayed to you.

Further information on the subject of qualifications can be found in the section of the same name.
Usage NoneThere is
no task scheduling, the fields are not editable in the project task.

Task planningYou
can enter planning directly in the project tasks.

ForecastThere is
no task planning, the fields are not editable in the project task.

BothYou
can enter planning directly in the project tasks.
Type planning Via the type of planning you determine the type with which the task planning is to be entered in the planning line.

You can choose from the following:
- Resource
- Article
- G/L account
Planning no. Via the planning no. you determine, depending on the type of planning, with which account the task planning is to be displayed in the planning line.
Work type code Specifies the work type code for the activity type.
Art Forecast Specifies the type forecast for the service type.

You can choose from the following:
• Resource
• Article
• G/L account
Forecastnr. Specifies the forecast no. in the context of the "Type Forcast" field.
Forecast work type code Specifies the forecast work type code.
Cross country skiing articles Identifies a project task with the assigned activity type as a "long-run item".

Project types#

When creating a new project, you can define the type of project by assigning a "project type". Here you can already enter some data such as a project template, order type or similar.

To define the project types in advance, call up the project types via the user search. Via "New" in the menu ribbon you can define a new project type with the help of the table below.

Stage Description
Code Assign a meaningful abbreviation for the project type.
Description Enter a description for the project type.
Project booking group Enter the project booking group for the project type to be used when assigning the project type.

Please note that if the "Template project no." is maintained (see below), this information is ignored. (see below) this information will be ignored.
Project number series Specify the project number series for the project type to be used when creating a project and assigning the project type.
Template Project No. Specifies the project no. to submit the project for the project type.
Project type Dimension value Specifies the dimension value for the project type.
Dimension code Specifies the dimension code.
Dimension Value Prefix Specifies the dimension value prefix.
Task breakdown Specifies a task breakdown for the project type.

Please note that if the "Template project no." is maintained (see above), this information is ignored. (see above) this information will be ignored.
Reserve Specifies the reservation method for the project type.

The following are available for selection:
• Never
• Optional
• Always
Order type In the project type, you can set up an order type for the creation of sales documents, if required. This will be used when creating the documents.

Project breakdown#

The project structure helps you to enter and maintain your project tasks quickly and efficiently with predefined numbering.

Call up the "Project outline" via the user search.

Via "New" you can create a new project outline using the table and procedure below.

Field Description
Code Define a unique code for the record here.
Description Define a short description for the outline here.
Status Indicates the status of the outline.

The following are available for selection:
• New
• Certified
• In development
• Expired

Note
Please note that only project members with the status "Certified" can be used in the processes.

To define the outline for the created dataset, call up the "Outline structure" menu item via the ribbon.

Field Description
Level Level or indentation of the task.
Description Enter a description for the layer here
Increase Define with which intervals the system should assign tasks, 1 for one step, 10 for ten steps etc.
Based on the increment, the Counter field is initialized.
Counter Here you can define with which value the level should be started and how wide the level can be. For example, enter 001 if the layer can reach a maximum value of 999. Please note that the Project task field only has a maximum width of 20 characters.
Separator Define a separator here, e.g. period, comma, hyphen
Count type • Numeric
• Alphanumeric
please specify alphanumeric if your counter contains letters.
Bookable Specify whether it is possible to post on the level
Example Represents the current definition, as a project task.

Project Document Text Template#

For easy editing/creation of the document texts in the projects, you can define project text templates in which you specify how and when which data record is to be printed in which document.

Note

Please note that pre- and post-texts on the project tasks are not passed on to subsequent documents. This is only possible with texts on project plan lines.

To do this, call up the "Project document templates" via the user search.

Via "New" you can create a new project document template using the table below.

Field Description
Project table Use this field to specify for which table the definition is valid.

The following selection is available:
• Project Task
• Project planning line
Line type Use this field to specify for which line type the definition is valid.

The following selection is available:
• Budget
• Invoiceable
• Budget and Invoiceable
Position In this field, specify how the definition is valid for which position.

The following selection is available:
• Pretext
• Post text
Service Contract Offer Printing In this field, specify whether the text should be printed on Service contract offer.
Service contract printing Use this field to specify whether the text should be printed on the service contract.
Service offer printing Use this field to specify whether the text should be printed on the service offer.
Service Order Printing Use this field to specify whether the text should be printed on the service order.
Service Geb. Invoice Printing Use this field to specify whether the text should be printed on the service invoice.
Service Geb. Credit Print Use this field to specify whether the text is to be printed on the service credit note.
Service Geb. Delivery Print In this field, specify whether the text is to be printed on the service delivery.
Service work ticket printing In this field, specify whether the text should be printed on service work ticket.
VK offer pressure In this field, specify whether the text should be printed on VK offer.
VK Order Printing Use this field to specify whether the text should be printed on VK Order.
VK Geb. Invoice Print Use this field to specify whether the text should be printed on VK Geb. Rechnung.
VK Geb. credit print Use this field to specify whether the text should be printed on VK Geb. Gutschrift.
VK Blanket order printing Use this field to specify whether the text should be printed on VK Blanket Order.

  1. Microsoft, Microsoft Dynamics, and Microsoft Dynamics 365 are trademarks of the Microsoft group of companies.